Integra Technologies Bel Aire site
Bel Aire, KS. Packaging and test.
Integra Technologies, headquartered in Wichita, KS
Integra Technologies Wichita-area OSAT plant and headquarters
Planned 1 million sq ft OSAT assembly and test plant in Bel Aire near Wichita; stalled awaiting CHIPS funding, state incentives expired Oct 2024, Micross bought Integra Jan 2025.
- Investment
- $1.8B
- Jobs
- 2,000
- Announced
- Feb 2, 2023
- Target
- not stated
- Type
- Packaging and test
- Process or product
- OSAT assembly, test and qualification
- Wafer size
- not stated
- CHIPS Act funding
- none on record
Timeline
- Funding
Sen. Moran's office said CHIPS funding had been offered to Integra, amount undisclosed; Micross was deciding whether it fits its plans.
KSNW via Yahoo Finance - Ownership change
Micross Components closed its acquisition of Integra Technologies.
Micross Components - Delay
The Kansas APEX incentive package expired with no federal CHIPS decision announced.
KWCH - Pause
KSN reported the plant was still on hold while Integra awaited federal CHIPS funding.
KSN - Announced
Kansas announced Integra's $1.8 billion, 1 million sq ft semiconductor packaging and test plant.
Kansas Department of Commerce
Sources (6)
- New developments in effort to build $2 billion semiconductor facility in Bel Aire KSNW via Yahoo Finance, Jan 28, 2025
- Micross Acquires Integra Technologies Micross Components, Jan 15, 2025
- Incentive package expires for Kansas company awaiting federal funding for expansion KWCH, Oct 1, 2024
- Integra update on plan to bring in $2 billion facility KSN, Apr 23, 2024
- Integra Technologies Kansas semiconductor project announcement Kansas Department of Commerce, Feb 2, 2023
- KS: Integra Technologies Selects Kansas for Largest OSAT Semiconductor Project, to Create 2,000 Jobs Trade and Industry Development
1 supplier or contractor on record for this project
Names, roles, and the source for each are in the US chip fab dataset.
Get told when this site changes
Get every project in one spreadsheet, with suppliers, contractors and sources, kept current. See the dataset. Or get the free Weekly Silicon brief:
Figures are what the company or an agency announced. "Not stated" means no source gives a number for this site. A status is only as current as its "as of" date.